EGF Sewage

June 29, 2012

A consultant is recommending East Grand Forks fine-tune its costs analysis with new methodology before deciding whether to upgrade its leaking lagoon system or adopt an interconnect project with Grand Forks.    MSA Professional Services Vice-President Gil Hantzsch says if the cost of the two alternatives are within ten-percent then non-monetary benefits of interconnection with Grand Forks appear to outweigh those of upgrading the East Grand Forks pond system.  Hantzsch says while the recommendation suggests the city make a decision based on a 20-year present value analysis the liklihood of pond technology being viable for the next 50 years appears remote.    The report was forwarded to city leaders this week.